Short answer: Under the Construction Act, the person paying you must send a payment notice within 5 days of each payment's due date. The notice says what they will pay and how they worked it out. If they don't send one, you can send your own notice and that becomes the sum due. If they want to pay less than the notified sum, they must send a pay less notice before a deadline: 7 days before the final date for payment, unless your contract sets a different period. Without a valid pay less notice, they must pay the notified sum in full by the final date. None of this applies to work for a homeowner on the home they live in, or intend to live in, and only where the contract principally relates to that home.
This guide is general information, not legal advice. Notices and deadlines depend on the exact wording of your contract, so if money is at stake, speak to a construction solicitor.
What the Construction Act is
"The Construction Act" usually means Part II of the Housing Grants, Construction and Regeneration Act 1996. It was amended by the Local Democracy, Economic Development and Construction Act 2009, and the changes took effect for contracts made from 1 October 2011 in England and Wales and 1 November 2011 in Scotland. It sets minimum payment rules for construction contracts.
Where a contract leaves out something the Act requires, the Scheme for Construction Contracts fills the gap. In England and Wales that is the Scheme for Construction Contracts (England and Wales) Regulations 1998, as amended. Scotland has its own Scheme, and Northern Ireland has separate law, the Construction Contracts (Northern Ireland) Order 1997. This guide uses the England and Wales Scheme for its default timings.
Does it apply to your job?
It applies to most agreements to carry out construction operations, such as building, altering, repairing, decorating and installing heating, electrics or drainage, whether you work for a main contractor, a developer or a commercial client. Since the 2011 changes, the contract no longer has to be in writing. The section that limited the Act to written contracts was repealed.
The residential occupier exclusion
The Act does not apply to a construction contract with a residential occupier. That means a contract that principally relates to work on a house or flat that the customer lives in, or intends to live in.
So if you build an extension for a couple on the house they live in, the Act's payment notice rules don't apply between you and them. Your quote and payment terms do the work instead. But:
- if you are a subcontractor on that same extension, working for the builder, your contract with the builder is not with a residential occupier, so the Act can apply to it
- if the customer is a landlord or a company, doing up a property they don't live in, the exclusion does not apply
Some other narrow categories of contract are excluded by order, for example certain water infrastructure contracts in Wales. These rarely affect smaller trade businesses.
The key terms in plain English
- Payee: the person being paid, often you as the subcontractor.
- Payer: the person paying, such as the main contractor or client.
- Due date: the date a payment becomes due under the contract.
- Final date for payment: the last day the payer can pay without being in breach.
- Notified sum: the amount in the valid payment notice, or in your own notice if the payer didn't send one. It is what the payer must pay unless they serve a valid pay less notice.
Stage payments and the default dates
If a job is expected to last 45 days or more, you are entitled to stage or periodic payments and the contract can set the amounts and intervals. If it doesn't, the Scheme's default rules apply:
- Payment period: 28 days, unless the contract sets another period.
- Due date for a stage payment: 7 days after the end of the period, or the date you make your claim, whichever is later.
- Due date for the final payment: 30 days after the work is completed, or the date you make your claim, whichever is later.
- Final date for payment: 17 days after the due date.
Every construction contract must have an adequate way of working out what is due and when, and a final date for payment. "Pay when paid" clauses, where you only get paid once the contractor has been paid by their client, are not effective unless someone up the chain is insolvent.
The payment notice
For every payment, the contract must require a payment notice no later than 5 days after the due date. Usually the payer sends it, but some contracts make the payee's application the payment notice. The notice must state:
- the sum the sender considers due at the due date
- the basis on which that sum is calculated
The sum can be zero, but the payer still has to explain how they got there. If the contract doesn't provide for a payment notice, the Scheme requires the payer to give one within 5 days of the due date.
If you don't get a payment notice: your default notice
If the payer was supposed to send a payment notice and didn't, you can send your own notice at any time afterwards. It should state the sum you consider due and how you worked it out. That sum becomes the notified sum. The final date for payment moves back by the number of days your notice was late.
If your contract allows you to send an application for payment before the payment notice deadline, and you did, that application counts as your notice automatically. That is one reason to send a clear, dated application or invoice, showing how each figure is worked out, before every due date.
The pay less notice
If the payer wants to pay less than the notified sum, they must send a notice of intention to pay less, usually called a pay less notice. It must state:
- the sum they consider due on the date the notice is sent (this can be zero)
- the basis on which that sum is calculated
It must be sent no later than the period agreed in the contract before the final date for payment. If the contract doesn't set a period, the Scheme says 7 days before the final date.
If there's no valid pay less notice in time, the payer must pay the notified sum by the final date. They can still dispute the work later, for example through adjudication, but they can't hold back the money without a valid notice.
A worked timeline
This example uses the England and Wales Scheme defaults and assumes the contract sets no dates of its own. When counting days, the Act says a period starts the day after the date it runs from, and leaves out Christmas Day, Good Friday and bank holidays. There are none in this example.
| Step | Rule (Scheme default) | Example date |
|---|---|---|
| Payment period ends, you send your claim | 28-day period | Friday 5 February 2027 |
| Due date | 7 days after the period ends, or the claim if later | Friday 12 February 2027 |
| Payer's payment notice deadline | No later than 5 days after the due date | Wednesday 17 February 2027 |
| Pay less notice deadline | No later than 7 days before the final date | Monday 22 February 2027 |
| Final date for payment | 17 days after the due date | Monday 1 March 2027 |
Check the dates against your own contract. Many contracts set different periods, and the contract wins where it complies with the Act.
If you still aren't paid
- Suspend work. If the notified sum isn't paid by the final date, you have a right to suspend some or all of your work after giving at least 7 days' notice of your intention to suspend. The notice must say why you are suspending, and putting it in writing gives you a record. The payer must cover your reasonable costs of the suspension, and you get extra time to finish. See also when to stop work if you haven't been paid.
- Adjudication. Either side can refer a dispute to an adjudicator, who must normally decide within 28 days of referral. The decision is binding until the dispute is finally settled in court, by arbitration or by agreement.
- Interest. Between businesses, statutory interest and fixed compensation can apply to late payments unless your contract sets its own interest rate. Our guide on charging interest on late invoices explains the options.
If the payer has sent a valid pay less notice and paid the lower amount, see what to do when a customer pays less than the invoice.
Changes going through Parliament
The government's Commercial Payments Bill would change parts of the Construction Act. Its proposals include banning retentions in construction contracts and making late payment interest compulsory. It is a government bill. It had its first reading in the House of Lords on 19 May 2026 and its third reading there on 20 October 2026, then its first reading in the House of Commons on 21 October 2026. It is now awaiting its second reading in the Commons. It is not law yet, so the rules above still apply.
Sole traders and limited companies
The payment notice rules are the same whether you trade as a sole trader, in a partnership or as a limited company. What matters is the contract and who your customer is. A customer that is a company is unlikely to count as a residential occupier, because the exclusion is about a party who lives, or intends to live, in the property. If you work through your own limited company, make sure your applications and invoices are in the company's full name, so the notices clearly relate to the right contract.
Where Pencil Assistant fits
Pencil Assistant doesn't send statutory notices and isn't legal software. What it does do is draft clear, dated, numbered invoices with labour and materials itemised, so the basis of your figures is set out when you need to rely on your application. It also tracks what's unpaid, so you can ask "what's due from the Morgan Homes job?" or "which invoices are past their final date?". It drafts the follow-up for you to send yourself. Pencil Assistant never messages customers or contractors for you. It's one plan at £20 a month, after a 7-day free trial.
Related guides
- when to stop work if you haven't been paid
- charging interest on late invoices
- what to do when a customer pays less than the invoice
- Payment terms to put on a trade quote and invoice: due on completion, 7, 14 or 30 days
- Is a WhatsApp invoice valid in the UK? What it must include for sole traders, limited companies and VAT-registered trades
