How retention works on building quotes and when to write it in

Retention is money you have already earned that they keep for a period after the job, usually against defects. If you agree it, write the percentage, the release dates, and that it is not a discount.

A 5% hold on a six-month defects period is a cashflow hit. Price it or refuse it. Do not discover it in a subcontract you skimmed on the tools.

Main contractor: “We always do 5% retention, 2.5% at PC, 2.5% at 12 months.” You quoted a tight number with no float. That 5% is your van for a year. Retention is not a moral failing. It is a term. Put it on the quote or walk.

What to write

TermMake it specific
Percent5% of each invoice, or 5% of the job — say which
First releasePractical completion / handover, defined
Second releaseEnd of defects period, date or months
What it is notNot a discount, not a snag they invent at month 11

Worked: job £40,000. Retention 5% = £2,000 sitting with them. If your margin was £2,400, you just lent them most of the profit until next spring. Either the rate includes that wait, or you do not sign it.

Retention: 5% of certified sums. 2.5% released on practical completion of our works; 2.5% released 6 months after, subject to defects we caused. Retention is not a discount on the quoted figure.

Domestic bathrooms rarely need retention. If a homeowner wants to “hold 10% until we’re happy,” that is a deposit in reverse with no end date. Use a snag visit and a defined callback instead. This is general information, not legal advice on JCT or other forms.

What people miss

Agreeing retention after you priced tight. Reprice, or say no. 5% of a thin job is a loss.

No release trigger. “When we’re happy” is never. Name completion and a month count.

Letting them keep it for their other trades’ defects. Your retention is for your works. Write that.

Forgetting it on the invoice. Show gross, retention held, amount due now — or you will chase the wrong figure.

Related guides

FAQ

Is 5% normal?
On some building contracts, yes. On a one-week domestic job, no. Match the job, not a forum.
Can I refuse retention?
Yes. Then they hire someone who priced it in. Your call.
VAT on retention?
Follow how you invoice the rest of the job. Do not invent a special VAT story for the held slice. Not tax advice.
They never pay the second half.
Diary the release date when you invoice. Chase it like any overdue invoice.

Create quotes and invoices from WhatsApp with Pencil assistant

Stop spending your Sunday evenings stuck behind a screen with a calculator. Dictate your site notes or snap a photo of your scribbles, and Pencil turns them into clear, professional PDFs you can check and send in seconds.

  • Turns quick voice notes or scribbled site photos into neat PDFs
  • Invoices sent on the spot so you get paid before you pack up
  • Adjust line items, labour, or VAT on the fly
Start 14-day free trial

No credit card required · Cancel anytime · 14-day trial

Pencil

WhatsApp

0:24

Alright Pencil, need a quote for Dave on High Street. Full repaint of the hall, stairs, and landing. Call it £220 for materials, 3 days labour at £200 a day, plus VAT. Address is 14 High Street, TN11 8LX.

PDFQuote_Dave_Decorating.pdfPDF

Quote for Dave Smith, TN11 8LX

Hall, stairs and landing repainting£600.00

Materials (paint, primer, protection)£220.00

Total: £820+VAT (£984)

Dave just called, he wants the 4 internal doors glossed as well. Add £120 labour for those and set the start date for next Thursday the 8th.
PDFQuote_Dave_Decorating_v2.pdfUpdated · PDF

Quote for Dave Smith, TN11 8LX

Hall, stairs and landing repainting£600.00

Materials (paint, primer, protection)£220.00

Gloss 4 internal doors£120.00

Total: £940+VAT (£1,128)

Start date: Thursday, 8th October

Preview of a UK decorator PDF quote generated with Pencil