How to quote additional work when a customer changes their mind mid-job

By Pencil Assistant

Stop the extra work. Send a short price on WhatsApp. Do not pick up a tool on the new bit until they say yes to a number.

If it is not on the original scope, it is not in the original price. A thumbs-up on the variation is enough if the amount is in that message.

They want a second radiator “while the floor is up.” Fair. It is not free because the compressor is already in the hall. The original quote did not include it. A clear scope on the first paper is what makes this conversation short instead of a row.

The sequence

StepOn siteOn WhatsApp
StopDo not start the extra“That’s extra to the quote.”
PriceFive minutes with the merchant app if neededLabour + materials + VAT, one figure
YesWaitThey reply yes to that figure
Do itThen pick the tools upPhoto or line on the invoice later

Copy this

That’s extra to the lounge quote. Second radiator, pipework, and making good: £380 + VAT. I can do it this afternoon if you reply YES to that figure. If not, I’ll finish what’s already agreed.

Small extras still get a number. “Only twenty minutes” is how you donate an hour plus a trip to Screwfix.

Happy to add the extra socket. £95 all in (labour, back box, making good). Reply yes and I’ll fit it before I pack up.

If they want to think overnight, pack the original job away cleanly. Do not leave the extra half-done as leverage. Come back when they have accepted.

What people miss

Sorting it at the end. Friday they remember a favour. You remember three extra hours. The chat needed a number on Tuesday.

Doing it because you are already there. Travel is sunk. Materials and time are not. Price them.

A vague “it’ll be a bit more.” They will hear “a bit.” You will mean £400. Put the figure.

Changing the job and not the paper. If the original was a quote, the extra needs its own acceptance. Same thread is fine.

Related guides

FAQ

What if they say yes in the room and never text?

Send the figure anyway: “As discussed, extra radiator £380 + VAT — reply yes to confirm.” Do the extra after that lands.

Tiny extras — still a message?

If you would notice it on the invoice, yes. A free five minutes becomes a free afternoon if it happens twice a week.

They refuse the extra price but still want it done.

Finish the original scope. Pack up. The extra waits for a number they accept.

Should I pause the whole job?

Only if the extra blocks the original work. Otherwise finish what was quoted, then the variation.

Get answers about your business from WhatsApp with Pencil Assistant

Stop guessing how the month’s going. Ask Pencil and it answers from your own diary, jobs, quotes and invoices, then gets the follow-ups, reminders and posts ready to win the work back.

  • Straight answers from your own jobs, quotes and invoices
  • Spots the quotes gone quiet and the regulars who are due
  • Gets the chasers, reminders and posts ready for you to send
Start your 7-day free trial

Cancel anytime · 7-day trial · Setup in 3 minutes

Pencil Assistant

WhatsApp

Have I had a quieter month?

A bit, yes. Compared to September:

- Jobs: 9 done for £3,780, down from 15 at £5,620

- Quotes: 6, down from 11

Most of the gap is boiler services: 6 last month, 1 so far this month. Everything else is about level.

What can we do about that?

Three things I’d start with:

1. Nudge on open quotes. The 5 total £2,950. The biggest is the £1,400 bathroom fit for Mrs Patel — we should go back with dates.

2. Check in on regulars. 11 customers had a boiler service with you last October or November and haven’t booked this year.

3. Get a post on Facebook groups. Boiler checks before winter are timely, and you’ve got free slots on 28, 29 and 30 October.

Want me to get all three ready?

👍