A useful daily building-job update says what was completed, what happens next, whether the programme has changed and what you need from the customer. Keep it factual, include a relevant photo where appropriate and give a time for the next update. If nothing has changed, say that too.
Use the templates below as a starting point. Replace every bracket, check the facts and send the message yourself. A progress message records the position; it is not a substitute for a quote, a formal variation or the notices required by your contract. For replies to quotes, follow-ups and mid-job extras, see the client objections and WhatsApp replies guides.
The four-line daily update
Hi [name], today's update for [job/address]: Done: [specific work completed]. Next: [next task and intended day]. Programme: [on the agreed programme / the change and its effect]. Needed from you: [decision/access/item and deadline, or 'nothing today']. [Photo attached, with a short explanation if useful.] Next update [day/time]. Thanks, [your name].
'First-fix pipework completed in the utility' tells the customer more than 'good progress'. Do not say an inspection passed, a room is safe to use or a stage is complete unless that is confirmed.
1. Start-of-job message
Send this once the start and access arrangements are actually confirmed.
Hi [name], we're confirmed to start [work] at [address] on [day, date], arriving [time/window]. First we'll [first task]. Please make sure [access, parking or preparation] is ready. We'll keep [agreed route/area] clear and explain any temporary restrictions when we arrive. I'll send a progress update [when]. If anything has changed at your end, please let me know before [time]. Thanks, [your name].
For a lived-in home, add the practical detail that matters: who has the key, which door to use and any agreed disruption. Do not promise 'no mess' or unrestricted access if that is not realistic.
A WhatsApp start message does not replace site planning. HSE's domestic-client guidance explains how construction health-and-safety duties can pass to the contractor or principal contractor on home projects. Keep the update consistent with the arrangements actually in place.
2. End-of-day progress update
Choose one of these two messages. Replace each field and remove any sentence that does not apply.
Option A — programme unchanged
Hi [name], we've completed [work] today and carried out [specific check/clear-up actually done]. Tomorrow we're planning [next task]. This depends on [real dependency]. The agreed completion date is unchanged. Please confirm [decision] by [time] so we can [next step]. I've attached [photo and what it shows]. I'll update you again [day/time].
Option B — revised completion date
Hi [name], we've completed [work] today and carried out [specific check/clear-up actually done]. Because [brief factual reason], the expected completion date is now [day/date]. Tomorrow we're planning [next task]. This depends on [real dependency]. Please confirm [decision] by [time] so we can [next step]. I've attached [photo and what it shows]. I'll update you again [day/time].
If there is no dependency, remove that sentence. If the customer does not need to decide anything, replace the request with 'Nothing needed from you tonight.' If no new completion date is confirmed, use the waiting-on-materials update below rather than inventing a date. These are progress summaries; follow the contract and the separate delay guide for any formal programme-change notice.
Only describe work as complete when it is. 'Tiles laid; grouting still to do' is clearer than 'bathroom finished' when it cannot yet be used.
3. Waiting on materials
Hi [name], [material/item] hasn't arrived as planned. The supplier's latest position is [confirmed date / no confirmed date yet]. This affects [specific task]. We can continue with [work], but [dependent work] has to wait. [The completion date is unchanged for now / I can't confirm the revised finish until delivery is confirmed.] I'll check again and update you by [day/time], even if there is no new date.
Do not convert 'expected Friday' into 'definitely Friday'. Say what is confirmed, what is only expected and what you will do next. Avoid blaming a supplier at length; the customer needs the impact and the next update.
For a job whose start has slipped, use the separate guide to communicating a delayed job. This template is for a live progress update, not a full rescheduling conversation.
4. Weather or site conditions have stopped a task
Hi [name], we couldn't carry out [task] today because [specific condition]. Carrying on would [brief factual reason, such as risk the finish or be unsafe]. We've [work actually done / left the affected area as described]. The next step is [check/action]. I'll review conditions [when] and update the programme by [time]. I'm not confirming a new completion date until [dependency] is clear.
Use this only where the condition genuinely affects the work. Do not claim a site is safe without checking it, or imply bad weather automatically allows an extra charge. Price and programme changes still need handling under the agreed contract.
5. A variation for approval before the extra work starts
Use a clear reference and send the priced scope, not just 'OK to go ahead?'. This is a message to accompany the variation, not a replacement for a detailed variation where the contract needs one.
Hi [name], variation [reference] is for [extra/change], separate from quote [reference]. It includes [scope] and excludes [exclusions]. The additional amount is [£net], VAT [£amount/correct treatment], total extra payable [£total]. This changes [stage/job total] to [£total] and has this effect on the programme: [state additional time or no expected change]. Please confirm explicitly that you accept this scope, additional total and programme change before I start the extra work. I'll continue [unaffected original work] in the meantime.
If you are not VAT registered, use 'Total extra payable £[amount]. No VAT charged — not VAT registered' instead of the net/VAT wording.
6. Written record after an approved variation
Send this only after the customer has actually approved the identified change.
Hi [name], thanks for confirming variation [reference] on [date]. As agreed, we're adding [scope] for [£total extra payable, with VAT position clear]. The agreed billing position is [revised total and when the extra will be billed]. The programme is now [date/unchanged]. I'll keep the agreed variation with the job records. Please flag anything here that does not match your understanding before the extra work starts.
Do not treat silence or an ambiguous emoji as reliable approval of every detail. Section 50 of the Consumer Rights Act explains why information about the service can form part of a consumer contract and why expressly agreed changes matter. For the pricing process, read how to quote additional work mid-job.
7. Handover with outstanding items made clear
Hi [name], [agreed work/stage] is ready for our handover review on [date/time]. We'll walk through [areas/items], explain [operation/care information] and record anything outstanding. [Documents actually available] will be provided by [method/time]. The current outstanding items are [list / 'none identified at today's check']. Please send any points you'd like us to look at before the visit. The balance and due date remain as shown on [invoice/contract reference].
Do not say a certificate is attached if you are still waiting for it. Do not label a project 'fully complete' while the message lists unfinished contracted work. A handover review is a chance to establish the position clearly, not to imply the customer has waived their rights.
8. Snagging visit and follow-up
Hi [name], I've recorded these items for the snagging visit: [short numbered list]. We're agreed for [day, date and time/window], subject to [access arrangements]. Please let me know before [time] if the list misses anything you have already raised. After the visit I'll confirm what has been completed and the next step for anything still outstanding.
After the visit:
Hi [name], today's snagging update: [items] completed. [Item] remains outstanding because [reason]. Next action is [action] by [date], and I'll update you [when]. Photos/[relevant documents] attached. Thanks, [your name].
Keep the record item by item. 'All sorted' is unhelpful if one promised return visit remains.
Keep updates short without leaving out the important bit
Send an update at the interval you agreed with the customer. Daily may suit a busy renovation; a smaller job may only need a start confirmation and a completion message. A significant delay or decision should not wait for the regular slot.
Useful photos show the work being described. Avoid unrelated people, private paperwork and belongings. Check that you are entitled to share the image and that it does not reveal unnecessary personal information. Keep updates with the relevant job reference, and retain a usable record of agreed changes rather than relying on a chat search months later.
Turn site notes into a draft, then check it
Pencil Assistant can draft replies and follow-ups from the information you give it. Try a voice note while parked safely:
Draft a short update for Customer A. Utility first fix done today. Tomorrow plasterboard, subject to the inspection being completed. Don't say the inspection has passed. Need their tap choice by noon. I'll check and send the message myself.
Check every claim, date and request before copying the draft to the customer. Pencil Assistant never messages customers. It is available through WhatsApp or the dashboard app and keeps your recorded jobs, customers, quotes, invoices and diary together. You can also ask about open quotes or invoiced income; those answers depend on the information recorded.
One plan costs £20/month after a 7-day free trial, subject to fair use and terms.
Related guides
Frequently asked questions
- What should a builder send as a daily progress update?
The work completed, the next task, any change to timing and any decision needed from the customer. Add a relevant photo if it clarifies the update and say when the next update will come.
- Should I update the customer if nothing has happened?
Yes, if they are waiting on a delivery, decision or revised date. Say there is no confirmed change and give the next check-in time. Silence forces them to chase information you already know they need.
- Can I use WhatsApp to agree additional work?
Use a clear written scope, price, tax position and timing, and obtain explicit agreement. Follow the contract's variation and notice requirements. A casual message is not automatically a substitute for every formal step.